| Seattle Municipal Tower. DPD is on the 20th floor. |
First, he was very concerned about the expired permit associated with the property from 2010. He said that we would need to resolve project #6240581, probably with a field inspection. That's the acronym we want: an STFI ("Subject to field inspection") permit that doesn't require plan review.
Update 3/1/15: We're already confused. I couldn't access 6461545 online, but I could start a new one 6461743. Now I can't access either online. Update: 3/2/15: I think we're settled on 6461743; I'll get them to retire 6461545.
Unwrapping the tangled, interrupt-driven conversation, we have:
1. Request a Pre-Application Site Visit ($142.50). The form needs to be accompanied with a site plan (max. 11" x 17") showing the entire lot and the proposed work. They accept fax, email, or mail or they have an online system. (Richard should have suggested that I pay the fee while I was there.)
2. File a Preliminary Application Form (PAF), which also needs a site plan. Not clear which comes first, but it probably doesn't matter. After the site visit, they'll file a site visit report, and that is required for step #3.
3. File a Request for Relief From Prohibition on Steep Slope Development or Modification to ECA Submittal Requirements. According to Richard, the property is in Environmentally Critical Area (ECA) for Steep Slope, Potential Slide, Known Slide, and Wildlife. Richard thought that the survey was missing a few ECA things, and I said I need to know what's missing, because the survey was sold as ECA compliant. Richard mumbled, well, it shows Top of Slope, but it doesn't show the 15' buffer zone from top of slope. He couldn't come up with anything else that was missing.
Richard said that they will bargain--ECA exemption, but you have to do a full plan review. Or, ECA exemption and no plan review required, but you have to submit a full geotechnical report. The starting point is that there is no development allowed in an ECA. This is supposedly explained in Tip #327A.
4. Then we can talk Construction Permit. Because the project is more than 300 SF being added, it won't get a Small Project exemption. But it might qualify for STFI if there are no beams over 14'. I said, we have a 16' garage door, and he said there's an exception for that. So, STFI if there are no beams over 14' except for garage door headers no wider than 16'. Nothing is definitive--it's STFI if they say so, not if they say it's not. What a zoo.
I took in a 1"=10' site plan showing proposed additions. I used A.9 except that I showed the Trees Room extending to the south wall of the main house. Also, I deliberately showed the garage 2' closer to the street. Richard picked up on that, but said it was a Zoning issue and I'd have to talk to them. He explained about the 15' buffer zone from top of slope, which makes me think that Trees Room could come even further south.