We had aimed for 25 March, but rain was forecast. Tuesday, 26 March, was dry, but I had already agreed with Mauricio (aka Odilio) that we would target starting on 29 March. It rained Wednesday, when I gave Mauricio a check for 25% ($5,000 and change), and again on Thursday, when ABC Supply showed up and unloaded tons of shingles, rolls of CertainTeed Diamond Deck and other miscellany.
 |
| Shingles delivered and stacked all over the roof. |
But Friday, 29 March, was clear and sunny and Mauricio showed up with 3 helpers and got to work. The four worked 30 March as well, but not 31 March--that was Easter Sunday. They left the big truck parked here.
 |
| Mauricio was surprised by the extent of the rot and had to bring more lumber with him on Saturday. I was actually pleased that so much of the OSB sheathing was in good shape. |
 |
| Notice the wide metal valley flashings on the ground |
Monday, 1 April, Mauricio was back with one helper--I think it's his son. Only the three west side roof planes remained to de-shingle. The Diamond Deck is already up on most of the main house.
 |
| Mauricio and (I think) his son standing behind him, working over the front porch |
 |
| CertainTeed Diamond Deck |